Method of statement for installation and testing of fire sprinkler system 

Scope

 this procedure covers installation and inspection of firefighting -sprinkler system

purpose

purpose of this procedure is to define the method of installation and inspection of sprinkler system

Quality control

Quality of installation and materials at site will be ensured by our project team consisting of project manger,project engineer,QA/QC engineer and the site foreman 

Quality of the work will be according to NFPA standards and civil defence authority requirements

Storage and handling 

The pipes will be stacked in the site store on a flat surface at a height not exceeding 1.7m from bottom layer

Fittings will be separately packed and stored as per the sizes required for the project 

All open ends  of pipes will be covered to protect from foreign matter,dirt/debris

Responsibilities/supervision

To ensure that all the preparation and application works are carried out according to the contract and manufacturers data sheet

To ensure that the progressing of works is carried out according to the planned program and as per the approved method statement

To ensure that all the equipments and materials required for executing the work are available according to the planned construction program

To co-ordinate with the main contractor MEP coordinator & safety officer for a safe and proper excusion  of the work

To provide all necessary information and to distribute responsibilities  to his construction team

The foreman will be responsible for

The foreman will carry out his duties by maintaining continuous coordination with project engineer on daily basis ,to ensure proper distribution of the work force in the required and planed locations 

To provide project engineer a daily progress report indicating the works achieved and discuss with him the planned activities for the next day 

To ensure that the daily work is progressing as planned and advise the project engineer of any requirement for additional resources 

To be aware of test frequencies related to pipe work and hydrostatic

To control disposal of waste materials according to the instruction received for the project engineer

To ensure full coordination with the safety officers to maintain safe working and proper housekeeping of the site,following the approved safety measures and further ensure that all his working team are aware of the same to prevent accident and losses

To inform the project engineer about the readiness of work for inspection and its checking if any

Tools&Equipment

The following tools and equipment will be used for fire fighting system installation

Grooving Machine

Threading Machine

Welding Machine

Hilti drill Machine Model TE-1 AND TE-24

and 12''Grinding Machine 

Vice Table

Pipe Wrenches

Fire fighting system description

Sprinkler system    : Definition

 An integrated system of underground and overhead piping designed in accordance with fire protection engineering standards .The portion of the sprinkler system above ground in a network of specially sized or hydraulically designed piping installed in a building ,structure,or area , generally overhead and to which sprinklers are attached in a systematic pattern.The valve controlling each system riser is located in the system riser or its supply piping .The system is activated by heat from a fire discharges water over the fire area

Wet Pipe System

A sprinkler system employing automatic sprinklers attached to a piping system containing water and connected to a water supply so that water discharges immediately from sprinkler opened by heat from a fire 

System Components

Network of pipes 

Zone control valve assembly

Sprinkler

Air release valve 

Fire Department connection 

  Minimum one four -way inlet branching connection-to 2 ½ ''fire hose and two-way

 inlet breaching connection to 1'' fire hose reel system will be connected to the accessibility to connect with fire department

Work Sequence and methodology

Installation of fire sprinkler system

The installation of fire sprinkler system shall be according to approved detailed shop drawings and also as per the recommendations of NFPA 13

Pipe hangers shall be spaced at intervals as specified in our approved shop drawings

Threaded piping will be made with Teflon tape or with a suitable pipe sealing compound -jute and mastic combination-applied 

two inches and below sizes of pipe are made threaded - two and half inches and above sizes are normally grooved type.groove can be made cut groove or roll groove

All underground fittings will be welded type .All piping coming underground will be wrapped with poly vinyl  chloride tape

 All piping must be rigidly supported by a combination network comprised of pipe hangers and rigid support brackets .The spacing will be as per the scheduled attached

Sprinkler head location shall be installed in accordance with approved system plans and coordinated RCP- Reflected Ceiling Plan- layout

Installation of sprinkler head

All the sprinkler heads must be installed according to current NFPA 13 standard

The system piping must be properly sized according to approved drawings and calculations to insure the maximum required flow rate at the sprinkler head

Install the sprinkler heads after the piping is in place to avoid mechanical damage 

In the event of a thread leak,remove the unit ,apply new pipe teflon tape,and reinstall

The face of the sprinkler fitting should be installed a nominal 3/8'' to 1'' behind the finished ceiling line,adjustment may be made via the push-on escutcheon plate to compensate for variation in the fittings

Hand tightens the sprinkler into the fitting using the proper size wrench

To install the escutcheon plate,align it with and press it over the sprinkler body until the outer edge of the escutcheon meets the mounting surface 

Installation of butterfly valve

The butterfly valve should be located as per the approved drawings,also to make sure that it is located where it will be readily accessible for operation ,inspection and maintenance

During installation make sure that the valve disc does not interfere with the operation of other systems components immediately adjacent to the butterfly valve

When a valve closes,it may be due to debris lodged in the sealing area .This may be corrected by blacking-off the hand wheel and closing it again,several times if necessary . the valve should never be forced to seat by applying a wrench to the hand wheel as this may distort the valve components or score the sealing surfaces

The inlet and outlet piping adjacent to the valve should be properly supported to prevent excessive stress on the valve body . The valve should not be used to force a pipeline into position as this may result in distortion of the valve body

Installation of the flow switch

The flow switch should be located as per approved drawings ,also to make sure that it is located where it will be readily accessible for operation,inspection and maintenance

The flow switch may be mounted on horizontal or vertical pipe. On horizontal pipe they should be installed on the top side of pipe where they will accessible

Drain the system and drill a hole in pipe using a circular saw in a slow speed drill the hole size shall be 2 inches

 Clean the inside pipe of all growth or other material for a distance equal to the pipe diameter on either side of hole

Roll the vane so that it may be inserted in the hole,do not bend or crease it

Insert the vanes so that the arrow on the saddle points in the direction of the water flow 

Install the saddle strap and tighten nuts alternately

The vane must not rub inside of the pipe or bind in any way 

Method of pressure testing systems piping

Sprinkler &Firefighting systems piping

Installation check

Hydro static Testing of pipe line

Test condition performance requirement

Test pressure :1.5 times of the working pressure 

Duration : 2 hrs.pressure 

Monitoring: By calibrated pressure gauge installed at the lowest element no visible leakage from external piping 

At the end of 2 hours Duration ,there should not be any remarkable change in system pressure 

Method of testing

Plug all the openings

Close all the drain valves

Fill complete pipeline with water avoiding any air column . For this purpose keep the drain valve at the highest elevation slightly open , while filing water when line is completely filled with water close the valve 

By a pressure pump pressurise the line to an intermediate pressure , say 100 psi .wait for 5 minutes ,check all major joints for any visible leak

 If the system is OK again pressurise the system  to 150 psi and wait for 10 minutes for any drop in pressure or leakage 

If the system is found to be leak proof  pressurise the line to the required testing pressure and keep for 2 hours

Functional testing for sprinkler system

Open the test valve on alarm check valve water motor alarm gong should be operate

Fire alarm system bell should ring 

Main pump should start

By a heat source operate remote sprinkler water should spray covering the area specified 

Main pump should start

Indication on fire alarm panel & repeater panel regarding the zone being operated 

Health and safety 